Read next Projects Under Implementation

IZDEHAR CCGT Power Plant

IZDEHAR | Palestine Prosperity Investment & Development|2025-02-02 13:20:02

Project Overview 


  • The project involves a power plant with an initial production capacity of 240 MW, expandable to 400 MW in the future
  • It includes two gas turbines and one steam turbine to increase electricity generation and availability by 15%
  • Annual electricity output is 1,300 GWh, aiming to reduce the electricity supply gap in Palestine
  • The project will meet the energy demands of industrial and manufacturing businesses, particularly heavy electricity consumers, ensuring reliable operation of large-scale plants


Impact


  • Direct jobs: 100 & Indirect jobs: 10 thousand
  • Reduce Palestine trade account deficit 
  • Economic  Independence
  • Enabling growth in industrial projects
  • Attracting regional  and international capitals  and financing


Project Timeline
Project Highlight

2021 -  Temporary license

kjlkjkl

3 Gas Turbine, 1 Gas Turbine, NG pipeline

2023 - Implementation Agreement Framework, and PPA

US $240 million investment

2024 -  Financial closing, project development

30% Equity

2024 - Continue development.

14% IRR

2026 Q2 - Gaz supply agreement, equipment quotations.


2027 - Financial Close, final agreement with PA


2028 - Project development


2031 - Electricity production